1 Figure 1 below shows an activity diagram for a cleaning project. The duration of each activity is given in days.
- Find the earliest start time and the latest finish time for each activity and insert their values on Figure 1.
- Find the critical paths and state the minimum time for completion of the project.
- Find the activity with the greatest float time and state the value of its float time.
- On Figure 2 opposite, draw a cascade diagram (Gantt chart) for the project, assuming that each activity starts as late as possible.
- \begin{figure}[h]
\captionsetup{labelformat=empty}
\caption{Figure 1}
\includegraphics[alt={},max width=\textwidth]{1aca4e91-d1b3-4a78-8880-e42a4fbf3ddb-02_846_1488_1391_292}
\end{figure}
\begin{figure}[h]
\includegraphics[alt={},max width=\textwidth]{1aca4e91-d1b3-4a78-8880-e42a4fbf3ddb-03_1295_1714_219_150}
\captionsetup{labelformat=empty}
\caption{Figure 2}
\end{figure}
\begin{figure}[h]
\captionsetup{labelformat=empty}
\caption{(d)}
\includegraphics[alt={},max width=\textwidth]{1aca4e91-d1b3-4a78-8880-e42a4fbf3ddb-03_1023_1584_1589_278}
\end{figure}