1 [Figures 1 and 2, printed on the insert, are provided for use in this question.]
Figure 1 shows the activity network and the duration, in days, of each activity for a particular project.
- On Figure 1:
- find the earliest start time for each activity;
- find the latest finish time for each activity.
- Find the float for activity \(G\).
- Find the critical paths and state the minimum time for completion.
- The number of workers required for each activity is shown in the table.
| Activity | \(A\) | \(B\) | \(C\) | \(D\) | \(E\) | \(F\) | \(G\) | \(H\) | \(I\) | \(J\) |
| Number of workers required | 2 | 2 | 3 | 2 | 3 | 2 | 1 | 3 | 5 | 2 |
Given that each activity starts as late as possible and assuming that there is no limit to the number of workers available, draw a resource histogram for the project on Figure 2, indicating clearly which activities take place at any given time.