OCR MEI D1 2013 January — Question 4

Exam BoardOCR MEI
ModuleD1 (Decision Mathematics 1)
Year2013
SessionJanuary
TopicFixed Point Iteration

4 A room has two windows which have the same height but different widths. Each window is to have one curtain. The table lists the tasks involved in making the two curtains, their durations, and their immediate predecessors. The durations assume that only one person is working on the activity.
TaskDuration (minutes)Immediate predecessor(s)
Ameasure windows5-
Bcalculate material required5A
Cchoose material15-
Dbuy material15B, C
Ecut material5D
Fstitch sides of wide curtain30E
Gstitch top of wide curtain30F
Hstitch sides of narrow curtain30E
Istitch top of narrow curtain15H
Jhang curtains and pin hems20G, I
Khem wide curtain30J
Lhem narrow curtain15J
Mfit curtains10K, L
  1. Draw an activity on arc network for these activities.
  2. Mark on your diagram the early time and the late time for each event. Give the minimum completion time and the critical activities. Kate and Pete have two rooms to curtain, each identical to that above. Tasks A, B, C and D only need to be completed once each. All other tasks will have two versions, one for room 1 and one for room 2, eg E1 and E2. Kate and Pete share the tasks between them so that each task is completed by only one person.
  3. Complete the diagram to show how the tasks can be shared between them, and scheduled, so that the project can be completed in the least possible time. Give that least possible time.
  4. How much extra help would be needed to curtain both rooms in the minimum completion time from part (ii)? Explain your answer.