230 questions
| Activity | Immediate predecessor(s) | Duration (weeks) |
| \(A\) | - | 10 |
| B | - | 5 |
| C | B | 12 |
| D | \(A\) | 8 |
| \(E\) | C, D | 4 |
| \(F\) | C, D | 3 |
| \(G\) | C, D | 7 |
| \(H\) | E, F | 8 |
| \(I\) | G | 6 |
| \(J\) | G | 15 |
| K | H, I | 5 |
| \(L\) | K | 4 |
| Activity | Duration (days) | Immediate Predecessors |
| \(A\) | 7 | - |
| B | 6 | - |
| C | 15 | - |
| D | 9 | \(A , B\) |
| \(E\) | 8 | D |
| \(F\) | 6 | C, D |
| G | 7 | C |
| H | 14 | \(E\) |
| \(I\) | 17 | \(F , G\) |
| \(J\) | 9 | H, I |
| K | 8 | \(I\) |
| L | 12 | J, K |
| Month | January | February | March | April | May |
| Number ordered | 1 | 3 | 3 | 5 | 2 |
| Activity | Must be preceded by |
| \(A\) | \(-\) |
| \(B\) | \(A\) |
| \(C\) | \(B\) |
| \(D\) | \(A, C\) |
| \(E\) | \(A\) |
| \(F\) | \(E\) |
| \(G\) | \(E\) |
| \(H\) | \(G\) |
| \(I\) | \(D, F\) |
| \(J\) | \(G, I\) |
| \(K\) | \(G, I\) |
| \(L\) | \(H, K\) |
| Activity | Immediately preceding activities |
| \(A\) | -- |
| \(B\) | -- |
| \(C\) | -- |
| \(D\) | \(A\) |
| \(E\) | \(A\) |
| \(F\) | \(B\) |
| \(G\) | \(B\) |
| \(H\) | \(C, D\) |
| \(I\) | \(E\) |
| \(J\) | \(F, H\) |
| \(K\) | \(G, J\) |
| \(L\) | \(G\) |
| \(M\) | \(L\) |
| \(N\) | \(L\) |
| Activity | Duration (days) | Immediate predecessors | |
| A | Build concrete frame | 10 | \(-\) |
| B | Lay bricks | 7 | A |
| C | Lay roof tiles | 10 | A |
| D | First fit electrics | 5 | B |
| E | First fit plumbing | 4 | B |
| F | Plastering | 6 | C, D, E |
| G | Second fit electrics | 3 | F |
| H | Second fit plumbing | 2 | F |
| I | Tiling | 10 | G, H |
| J | Fit sanitary ware | 2 | H |
| K | Fit windows and doors | 5 | I |
| Activity | Depends on | Duration (hours) |
| \(A\) | \(-\) | 5 |
| \(B\) | \(A\) | 4 |
| \(C\) | \(A\) | 2 |
| \(D\) | \(B, C\) | 11 |
| \(E\) | \(C\) | 4 |
| \(F\) | \(D\) | 3 |
| \(G\) | \(D\) | 8 |
| \(H\) | \(D, E\) | 2 |
| \(I\) | \(F\) | 1 |
| \(J\) | \(F, G, H\) | 7 |
| \(K\) | \(I, J\) | 2 |
| Week | 1 | 2 | 3 |
| Shows | A, B, C | D, E | F, G, H |
| Show | \(A\) | \(B\) | \(C\) | \(D\) | \(E\) | \(F\) | \(G\) | \(H\) |
| Expected Profit (£) | 900 | 800 | 1000 | 1500 | 1300 | 500 | 700 | 600 |
| Travel costs (£) | \(A\) | \(B\) | \(C\) | \(D\) | \(E\) | \(F\) | \(G\) | \(H\) |
| Home | 70 | 80 | 150 | 80 | 90 | 70 | ||
| \(A\) | 180 | 150 | ||||||
| \(B\) | 140 | 120 | ||||||
| \(C\) | 200 | 210 | ||||||
| \(D\) | 200 | 160 | 120 | |||||
| \(E\) | 170 | 100 | 110 |
| Finishing point | ||||||||
| C | D | E | F | G | H | I | ||
| \multirow{3}{*}{Starting point} | A | 1 | 4.5 | 13 | 10 | 8 | 11 | 4 |
| B | 5 | 10.5 | ||||||
| C | 9 | 6 | ||||||
| D | 12 | 7 | 15 | |||||
| E | ||||||||
| F | 5 | |||||||
| G | 8 | |||||||
| H | 10 | |||||||
| I | ||||||||
| J | ||||||||
| K |
| Finishing point | |||||
| J | K | L | |||
| 2 | |||||
| 9 | 2 | 3 | |||
| 2 | 9 | ||||
| 5 | |||||
| 6 | |||||
| 10 |
| Activity | Time | Precedence |
| A | 5 | |
| B | 20 | A |
| C | 3 | A |
| D | 7 | A |
| E | 4 | B |
| F | 15 | C |
| G | 6 | C |
| H | 17 | D |
| I | 10 | F, G |
| J | 2 | G, H |
| K | 6 | E, I |
| L | 9 | I, J |
| M | 3 | K, L |