Critical Path Analysis
6
Find the earliest start time and the latest finish time for each activity and show these values on the activity network above.
6
(ii) Identify all of the critical activities.
6
The manager of Bill Durrh Ltd recruits some additional temporary workers in order to reduce the duration of one activity by 2 weeks.
The manager wants to reduce the minimum completion time of the project by the largest amount.
State, with a reason, which activity the manager should choose.