6
    1. Find the earliest start time and the latest finish time for each activity and show these values on the activity network above. 6
  1. (ii) Identify all of the critical activities. 6
  2. The manager of Bill Durrh Ltd recruits some additional temporary workers in order to reduce the duration of one activity by 2 weeks. The manager wants to reduce the minimum completion time of the project by the largest amount. State, with a reason, which activity the manager should choose.