AQA Further AS Paper 2 Discrete 2021 June — Question 1

Exam BoardAQA
ModuleFurther AS Paper 2 Discrete (Further AS Paper 2 Discrete)
Year2021
SessionJune
TopicCritical Path Analysis

1
  1. A project consists of three activities \(A , B\) and \(C\)
    An activity network for the project is shown in the diagram below.
    \includegraphics[max width=\textwidth, alt={}, center]{18ce34aa-e4c3-4a84-a36d-6542d2319bf5-02_615_770_726_635} Find the value of \(x\) Circle your answer.
    5
    7
    8
    12 1
  2. Find the value of \(y\)
    Circle your answer.
    5
    7
    8
    15