AQA
Further AS Paper 2 Discrete
2021
June
— Question 1
Exam Board
AQA
Module
Further AS Paper 2 Discrete (Further AS Paper 2 Discrete)
Year
2021
Session
June
Topic
Critical Path Analysis
1
A project consists of three activities \(A , B\) and \(C\)
An activity network for the project is shown in the diagram below.
\includegraphics[max width=\textwidth, alt={}, center]{18ce34aa-e4c3-4a84-a36d-6542d2319bf5-02_615_770_726_635}
Find the value of \(x\)
Circle your answer.
5
7
8
12
1
Find the value of \(y\)
Circle your answer.
5
7
8
15