AQA D2 2006 January — Question 3 18 marks

Exam BoardAQA
ModuleD2 (Decision Mathematics 2)
Year2006
SessionJanuary
Marks18
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicCritical Path Analysis
TypeDraw resource histogram
DifficultyModerate -0.3 This is a comprehensive but standard Critical Path Analysis question covering all routine techniques (network drawing, forward/backward pass, critical path, float, resource histogram, and basic resource levelling). While lengthy with multiple parts, each step follows textbook procedures with no novel problem-solving required, making it slightly easier than average for A-level.
Spec7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities7.05c Total float: calculation and interpretation7.05d Latest start and earliest finish: independent and interfering float7.05e Cascade charts: scheduling and effect of delays

3 [Figures 1 and 2, printed on the insert, are provided for use in this question.] A building project is to be undertaken. The table shows the activities involved.
ActivityImmediate PredecessorsDuration (days)Number of Workers Required
A-23
BA42
CA61
D\(B , C\)83
EC32
FD22
GD, E42
HD, E61
I\(F , G , H\)23
  1. Complete the activity network for the project on Figure 1.
  2. Find the earliest start time for each activity.
  3. Find the latest finish time for each activity.
  4. Find the critical path and state the minimum time for completion.
  5. State the float time for each non-critical activity.
  6. Given that each activity starts as early as possible, draw a resource histogram for the project on Figure 2.
  7. There are only 3 workers available at any time. Use resource levelling to explain why the project will overrun and state the minimum extra time required.

Question 3:
Part (a)
AnswerMarks Guidance
AnswerMarks Guidance
Activity network SCAM1
Almost correct (up to 2 slips)A1
All correctA1 3
Part (b)
AnswerMarks Guidance
AnswerMarks Guidance
Forward pass for earliest timesM1
CorrectA1 2
Part (c)
AnswerMarks Guidance
AnswerMarks Guidance
Backward passM1
CorrectA1 2
Part (d)
AnswerMarks Guidance
AnswerMarks Guidance
Critical path is \(ACDHI\)B1
Minimum completion 24 daysB1 2
Part (e)
AnswerMarks Guidance
AnswerMarks Guidance
Non-critical activities \(B,\ E,\ F,\ G\) with floats \(2,\ 5,\ 4,\ 2\) respectivelyM1 At least 3 activities and float in one activity correct
Correct earliest and latest times shown\(A1\sqrt{}\) 2 – \(\sqrt{}\) their earliest and latest times
Part (f)
AnswerMarks Guidance
AnswerMarks Guidance
Resource histogram \(\leq 11\)M1
CorrectA1
Rest as histogram – generally start activities okM1
All correctA1 4
Part (g)
AnswerMarks Guidance
AnswerMarks Guidance
Problems with \(D\ \&\ E\) solved by \(E\) coming after \(D\)M1
Problem at 16–18 days with \(F\) can be solved by moving \(F\) to 20–22A1
Must overrun by equivalent to duration of \(E\) (3 days)B1 3
## Question 3:

### Part (a)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Activity network SCA | M1 | |
| Almost correct (up to 2 slips) | A1 | |
| All correct | A1 | **3** |

### Part (b)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Forward pass for earliest times | M1 | |
| Correct | A1 | **2** |

### Part (c)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Backward pass | M1 | |
| Correct | A1 | **2** |

### Part (d)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Critical path is $ACDHI$ | B1 | |
| Minimum completion 24 days | B1 | **2** |

### Part (e)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Non-critical activities $B,\ E,\ F,\ G$ with floats $2,\ 5,\ 4,\ 2$ respectively | M1 | At least 3 activities and float in one activity correct |
| Correct earliest and latest times shown | $A1\sqrt{}$ | **2** – $\sqrt{}$ their earliest and latest times |

### Part (f)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Resource histogram $\leq 11$ | M1 | |
| Correct | A1 | |
| Rest as histogram – generally start activities ok | M1 | |
| All correct | A1 | **4** |

### Part (g)
| Answer | Marks | Guidance |
|--------|-------|----------|
| Problems with $D\ \&\ E$ solved by $E$ coming after $D$ | M1 | |
| Problem at 16–18 days with $F$ can be solved by moving $F$ to 20–22 | A1 | |
| Must overrun by equivalent to duration of $E$ (3 days) | B1 | **3** |

---
3 [Figures 1 and 2, printed on the insert, are provided for use in this question.] A building project is to be undertaken. The table shows the activities involved.

\begin{center}
\begin{tabular}{|l|l|l|l|}
\hline
Activity & Immediate Predecessors & Duration (days) & Number of Workers Required \\
\hline
A & - & 2 & 3 \\
\hline
B & A & 4 & 2 \\
\hline
C & A & 6 & 1 \\
\hline
D & $B , C$ & 8 & 3 \\
\hline
E & C & 3 & 2 \\
\hline
F & D & 2 & 2 \\
\hline
G & D, E & 4 & 2 \\
\hline
H & D, E & 6 & 1 \\
\hline
I & $F , G , H$ & 2 & 3 \\
\hline
\end{tabular}
\end{center}
\begin{enumerate}[label=(\alph*)]
\item Complete the activity network for the project on Figure 1.
\item Find the earliest start time for each activity.
\item Find the latest finish time for each activity.
\item Find the critical path and state the minimum time for completion.
\item State the float time for each non-critical activity.
\item Given that each activity starts as early as possible, draw a resource histogram for the project on Figure 2.
\item There are only 3 workers available at any time. Use resource levelling to explain why the project will overrun and state the minimum extra time required.
\end{enumerate}

\hfill \mbox{\textit{AQA D2 2006 Q3 [18]}}