Critical Path Analysis
Q2
Edexcel D1 2005 January — Question 2
Exam Board
Edexcel
Module
D1 (Decision Mathematics 1)
Year
2005
Session
January
Topic
Critical Path Analysis
2. The precedence table for activities involved in producing a computer game is shown below.
Activity
Must be preceded by
A
-
B
-
C
\(B\)
D
A, C
E
\(A\)
\(F\)
E
\(G\)
E
H
G
I
D, F
J
G, I
K
G, I
\(L\)
H, K
An activity on arc network is to be drawn to model this production process.
Explain why it is necessary to use at least two dummies when drawing the activity network.
(2)
Draw the activity network using exactly two dummies.
(5)