| Exam Board | Edexcel |
|---|---|
| Module | D1 (Decision Mathematics 1) |
| Year | 2021 |
| Session | January |
| Marks | 13 |
| Paper | Download PDF ↗ |
| Mark scheme | Download PDF ↗ |
| Topic | Critical Path Analysis |
| Type | Calculate early and late times |
| Difficulty | Moderate -0.3 This is a standard Critical Path Analysis question covering routine D1 techniques: completing an activity network, calculating early/late times, identifying critical activities, finding a lower bound for workers, and scheduling. While multi-part with several steps, each component is a textbook application of well-practiced algorithms with no novel problem-solving required. Slightly easier than average due to the mechanical nature of the procedures. |
| Spec | 7.05a Critical path analysis: activity on arc networks7.05b Forward and backward pass: earliest/latest times, critical activities |
| Activity | Duration (days) | Immediately preceding activities |
| A | 4 | - |
| B | 7 | - |
| C | 6 | - |
| D | 10 | A |
| E | 5 | A |
| F | 7 | C |
| G | 6 | B, C, E |
| H | 6 | B, C, E |
| I | 7 | B, C, E |
| J | 9 | D, H |
| K | 8 | B, C, E |
| L | 4 | F, G, K |
| M | 6 | F, G, K |
| N | 7 | F, G |
| P | 5 | M, N |
| Answer | Marks | Guidance |
|---|---|---|
| Answer/Working | Mark | Guidance |
| Any two of the five arcs (G, H, I or the two dummies) drawn correctly | B1 | Activities labelled with correct letter; dummies as dashed lines with no weight |
| Four of the five arcs drawn correctly | B1 | Activities labelled correctly; dummies as dashed lines |
| All five arcs (G, H, I and two dummies) drawn correctly with no extras; correct arrows, correct weights | B1 | CSO — all arrows must be present |
| All top boxes complete, values generally increasing in direction of arrows | M1 | Condone lack of 0 for M mark; dependent on first mark in (a) |
| All values in top boxes correct | A1 | CAO |
| All bottom boxes complete, values generally decreasing opposite to arrow direction | M1 | Condone lack of 28/0; dependent on first mark in (a) |
| All values in bottom boxes correct | A1 | CAO |
| Answer | Marks | Guidance |
|---|---|---|
| Answer/Working | Mark | Guidance |
| Critical activities: A, E, K, M, P | B1 | CAO — these five activities only |
| Answer | Marks | Guidance |
|---|---|---|
| Answer/Working | Mark | Guidance |
| Lower bound \(= \dfrac{97}{28} = 3.46\ldots\) so 4 workers | M1 A1 | M1 for attempt at lower bound using value in \([87-107]\) divided by finish time; A1 CSO — correct calculation seen or awrt 3.5 then 4 |
| Answer | Marks | Guidance |
|---|---|---|
| Answer/Working | Mark | Guidance |
| Not a cascade: Gantt chart with 5 workers used, at most, at least 11 activities placed | M1 | |
| 4 workers; all 15 activities present (just once); condone at most two errors | A1 | |
| 4 workers; all 15 activities present (just once); no errors | A1 |
# Question 6:
## Parts (a) and (b)
| Answer/Working | Mark | Guidance |
|---|---|---|
| Any two of the five arcs (G, H, I or the two dummies) drawn correctly | B1 | Activities labelled with correct letter; dummies as dashed lines with no weight |
| Four of the five arcs drawn correctly | B1 | Activities labelled correctly; dummies as dashed lines |
| All five arcs (G, H, I and two dummies) drawn correctly with no extras; correct arrows, correct weights | B1 | CSO — all arrows must be present |
| All top boxes complete, values generally increasing in direction of arrows | M1 | Condone lack of 0 for M mark; dependent on first mark in (a) |
| All values in top boxes correct | A1 | CAO |
| All bottom boxes complete, values generally decreasing opposite to arrow direction | M1 | Condone lack of 28/0; dependent on first mark in (a) |
| All values in bottom boxes correct | A1 | CAO |
## Part (c)
| Answer/Working | Mark | Guidance |
|---|---|---|
| Critical activities: A, E, K, M, P | B1 | CAO — these five activities only |
## Part (d)
| Answer/Working | Mark | Guidance |
|---|---|---|
| Lower bound $= \dfrac{97}{28} = 3.46\ldots$ so 4 workers | M1 A1 | M1 for attempt at lower bound using value in $[87-107]$ divided by finish time; A1 CSO — correct calculation seen or awrt 3.5 then 4 |
## Part (e)
| Answer/Working | Mark | Guidance |
|---|---|---|
| Not a cascade: Gantt chart with 5 workers used, at most, at least 11 activities placed | M1 | |
| 4 workers; all 15 activities present (just once); condone at most two errors | A1 | |
| 4 workers; all 15 activities present (just once); no errors | A1 | |
---
6.
\begin{center}
\begin{tabular}{|l|l|l|}
\hline
Activity & Duration (days) & Immediately preceding activities \\
\hline
A & 4 & - \\
\hline
B & 7 & - \\
\hline
C & 6 & - \\
\hline
D & 10 & A \\
\hline
E & 5 & A \\
\hline
F & 7 & C \\
\hline
G & 6 & B, C, E \\
\hline
H & 6 & B, C, E \\
\hline
I & 7 & B, C, E \\
\hline
J & 9 & D, H \\
\hline
K & 8 & B, C, E \\
\hline
L & 4 & F, G, K \\
\hline
M & 6 & F, G, K \\
\hline
N & 7 & F, G \\
\hline
P & 5 & M, N \\
\hline
\end{tabular}
\end{center}
The table above shows the activities required for the completion of a building project. For each activity the table shows the duration, in days, and the immediately preceding activities. Each activity requires one worker. The project is to be completed in the shortest possible time.
\begin{figure}[h]
\begin{center}
\includegraphics[alt={},max width=\textwidth]{48e785c0-7de5-450f-862c-4dd4d169adf9-08_668_1271_1658_397}
\captionsetup{labelformat=empty}
\caption{Figure 2}
\end{center}
\end{figure}
Figure 2 shows a partially completed activity network used to model the project. The activities are represented by the arcs and the numbers in brackets on the arcs are the times taken, in days, to complete each activity.
\begin{enumerate}[label=(\alph*)]
\item Complete the network in Diagram 1 in the answer book by adding activities $\mathrm { G } , \mathrm { H }$ and I and the minimum number of dummies.
\item Add the early event times and the late event times to Diagram 1 in the answer book.
\item State the critical activities.
\item Calculate a lower bound for the number of workers needed to complete the project in the shortest possible time. You must show your working.
\item Schedule the activities on Grid 1 in the answer book, using the minimum number of workers, so that the project is completed in the minimum time.
\end{enumerate}
\hfill \mbox{\textit{Edexcel D1 2021 Q6 [13]}}