OCR D2 2014 June — Question 5 2 marks

Exam BoardOCR
ModuleD2 (Decision Mathematics 2)
Year2014
SessionJune
Marks2
TopicSequences and Series

5 Following a promotion at work, Khalid needs to clear out his office to move to a different building. The activities involved, their durations (in hours) and immediate predecessors are listed in the table below. You may assume that some of Khalid's friends will help him and that once an activity is started it will be continued until it is completed.
ActivityDuration (hours)Immediate predecessors
ASort through cupboard and throw out rubbish4-
BGet packing boxes1-
CSort out items from desk and throw out rubbish3-
DPack remaining items from cupboard in boxes2\(A\), \(B\)
EPut personal items from desk into briefcase0.5C
\(F\)Pack remaining items from desk in boxes1.5\(B , C\)
GTake certificates down and put into briefcase1-
HLabel boxes to be stored0.5D, F
  1. Represent this project using an activity network.
  2. Carry out a forward pass and a backward pass through the activity network, showing the early event time and late event time at each vertex of your network. State the minimum project completion time and list the critical activities.
  3. How much longer could be spent on sorting the items from the desk and throwing out the rubbish (activity \(C\) ) without it affecting the overall completion time? Khalid says that he needs to do activities \(A , C , E\) and \(G\) himself. These activities take a total of 8.5 hours.
  4. By considering what happens if Khalid does \(A\) first, and what happens if he does \(C\) first, show that the project will take more than 8.5 hours.
  5. Draw up a schedule to show how just two people, Khalid and his friend Mia, can complete the project in 9 hours. Khalid must do \(A , C , E\) and \(G\) and activities cannot be shared between Khalid and Mia. [2]