OCR MEI D1 2011 June — Question 5

Exam BoardOCR MEI
ModuleD1 (Decision Mathematics 1)
Year2011
SessionJune
TopicCritical Path Analysis

5 The activity network and table together show the tasks involved in constructing a house extension, their durations and precedences.
\includegraphics[max width=\textwidth, alt={}, center]{2e03f6fb-69db-438a-a79e-3e04fab0d08a-5_231_985_338_539}
ActivityDescriptionDuration (days)
AArchitect produces plans10
PlObtain planning permission14
DemoDemolish existing structure3
FoExcavate foundations4
WBuild walls3
PbInstall plumbing2
RConstruct roof3
FlLay floor2
EFit electrics2
WDInstall windows and doors1
DecoDecorate5
  1. Show the immediate predecessors for each activity.
  2. Perform a forward pass and a backward pass to find the early time and the late time for each event.
  3. Give the critical activities, the project duration, and the total float for each activity.
  4. The activity network includes one dummy activity. Explain why this dummy activity is needed. Whilst the foundations are being dug the customer negotiates the installation of a decorative corbel. This will take one day. It must be done after the walls have been built, and before the roof is constructed. The windows and doors cannot be installed until it is completed. It will not have any effect on the construction of the floor.
  5. Redraw the activity network incorporating this extra activity.
  6. Find the revised critical activities and the revised project duration.