Edexcel D1 2004 January — Question 8

Exam BoardEdexcel
ModuleD1 (Decision Mathematics 1)
Year2004
SessionJanuary
TopicCombinations & Selection

8. \begin{figure}[h]
\captionsetup{labelformat=empty} \caption{Figure 4} \includegraphics[alt={},max width=\textwidth]{a21a4565-800c-45c0-a513-bb813ef1086f-8_864_1705_356_173}
\end{figure} A trainee at a building company is using critical path analysis to help plan a project. Figure 4 shows the trainee's activity network. Each activity is represented by an arc and the number in brackets on each arc is the duration of the activity, in hours.
  1. Find the values of \(x , y\) and \(z\).
  2. State the total length of the project and list the critical activities.
  3. Calculate the total float time on
    1. activity \(N\),
    2. activity \(H\).
      (3) The trainee's activity network is checked by the supervisor who finds a number of errors and omissions in the diagram. The project should be represented by the following precedence table.
      ActivityMust be preceded by:Duration
      A-4
      B-3
      C-5
      DB2
      EA, \(D\)8
      \(F\)B2
      GC2
      \(H\)C3
      I\(F , G\)4
      J\(F , G\)2
      K\(F , G\)7
      LE, I9
      MH, J3
      NE, I, K, M3
      \(P\)E, \(I\)6
      \(Q\)H, J5
      \(R\)\(Q\)7
  4. By adding activities and dummies amend the diagram in the answer book so that it represents the precedence table. (The durations of activities \(A , B , \ldots , N\) are all correctly given on the diagram in the answer book.)
  5. Find the total time needed to complete this project.