OCR Further Discrete AS 2019 June — Question 4

Exam BoardOCR
ModuleFurther Discrete AS (Further Discrete AS)
Year2019
SessionJune
TopicSequences and Series

4 The table shows the activities involved in a project, their durations in hours and their immediate predecessors. The activities can be represented as an activity network.
ActivityABCDEFGH
Duration24543324
Immediate predecessors-A-A, CB, CB, DD, EF, G
  1. Use standard algorithms to find the activities that form
    • the longest path(s)
    • the shortest path(s)
      through the activity network.
    You must show working to demonstrate the use of the algorithms. Only one of the paths from part (a) has a practical interpretation.
  2. What is the practical interpretation of the total weight of that path? The duration of activity E can be changed. No other durations change.
  3. What is the smallest increase to the duration of E that will make activity E become part of a longest path through the network?