OCR S4 2007 June — Question 3 7 marks

Exam BoardOCR
ModuleS4 (Statistics 4)
Year2007
SessionJune
Marks7
PaperDownload PDF ↗
Mark schemeDownload PDF ↗
TopicDiscrete Random Variables
TypeJoint distribution with covariance calculation
DifficultyStandard +0.3 This is a straightforward joint distribution question requiring routine calculations of marginal distributions, expectations, and covariance using standard formulas. Part (i) involves mechanical computation of E(XY) - E(X)E(Y), while part (ii) is direct application of conditional probability. No problem-solving insight needed, just careful arithmetic with a provided table.
Spec5.04a Linear combinations: E(aX+bY), Var(aX+bY)

3 The discrete random variables \(X\) and \(Y\) have the joint probability distribution given in the following table.
\(X\)
\cline { 2 - 5 } \multicolumn{1}{l}{}- 101
10.240.220.04
20.260.180.06
  1. Show that \(\operatorname { Cov } ( X , Y ) = 0\).
  2. Find the conditional distribution of \(X\) given that \(Y = 2\).

Question 3:
Part (i)
AnswerMarks Guidance
AnswerMark Guidance
Substantially correct network diagram with activities A, B, C, D, E, F, G and dummy activitiesM1 Condone arrows missing or wrong way round, no end and/or extra dummies. Do NOT allow activity on node formulation
Correct network with arrows on at least the dummy activities, no extra dummies and a single end pointA1
A dummy is needed after \(C\) because \(D\) follows both \(B\) and \(C\)B1 A valid explanation
A dummy is needed after \(D\) because \(F\) and \(G\) both follow \(D\)B1 A valid explanation
4
Part (ii)
AnswerMarks Guidance
AnswerMark Guidance
Substantially correct forward passM1
Early event times correct (ft their network if possible)A1
Substantially correct backwards passM1
Late event times correct (ft their network if possible)A1
Minimum completion time \(= 14\) daysB1 For 14, cao
Critical activities are \(A, C, D, F\)B1 For these four activities and no others, cao. In both cases these need to be stated, not implied from the diagram
6
Part (iii)
AnswerMarks Guidance
AnswerMark Guidance
Resource histogram showing number of workers for different activities, with scales and labels, some days with 4 workersM1 For a reasonable attempt at using the number of workers for the different activities
Reasonable attempt with no overhanging blocksM1 dep
Entirely correct histogramA1
3
Part (iv)
AnswerMarks Guidance
AnswerMark Guidance
\(E\) cannot happen until after \(C\) has finished so must overlap with \(F\)B1 Earliest finish for \(E >\) latest start for \(F\)
Start \(E\) immediately after \(C\) but delay the start of \(F\) for 1 day (until after \(E\) has finished)B1 For delaying the start of \(F\) (by 1 day)
2/15
# Question 3:

## Part (i)

| Answer | Mark | Guidance |
|--------|------|----------|
| Substantially correct network diagram with activities A, B, C, D, E, F, G and dummy activities | M1 | Condone arrows missing or wrong way round, no end and/or extra dummies. Do NOT allow activity on node formulation |
| Correct network with arrows on at least the dummy activities, no extra dummies and a single end point | A1 | |
| A dummy is needed after $C$ because $D$ follows both $B$ and $C$ | B1 | A valid explanation |
| A dummy is needed after $D$ because $F$ and $G$ both follow $D$ | B1 | A valid explanation |
| | **4** | |

## Part (ii)

| Answer | Mark | Guidance |
|--------|------|----------|
| Substantially correct forward pass | M1 | |
| Early event times correct (ft their network if possible) | A1 | |
| Substantially correct backwards pass | M1 | |
| Late event times correct (ft their network if possible) | A1 | |
| Minimum completion time $= 14$ days | B1 | For 14, cao |
| Critical activities are $A, C, D, F$ | B1 | For these four activities and no others, cao. In both cases these need to be stated, not implied from the diagram |
| | **6** | |

## Part (iii)

| Answer | Mark | Guidance |
|--------|------|----------|
| Resource histogram showing number of workers for different activities, with scales and labels, some days with 4 workers | M1 | For a reasonable attempt at using the number of workers for the different activities |
| Reasonable attempt with no overhanging blocks | M1 dep | |
| Entirely correct histogram | A1 | |
| | **3** | |

## Part (iv)

| Answer | Mark | Guidance |
|--------|------|----------|
| $E$ cannot happen until after $C$ has finished so must overlap with $F$ | B1 | Earliest finish for $E >$ latest start for $F$ |
| Start $E$ immediately after $C$ but delay the start of $F$ for 1 day (until after $E$ has finished) | B1 | For delaying the start of $F$ (by 1 day) |
| | **2/15** | |

---
3 The discrete random variables $X$ and $Y$ have the joint probability distribution given in the following table.

\begin{center}
\begin{tabular}{ c | c | c c c | }
\multicolumn{1}{c}{} & \multicolumn{2}{c}{$X$} &  \\
\cline { 2 - 5 }
\multicolumn{1}{l}{} & - 1 & 0 & 1 \\
\hline
1 & 0.24 & 0.22 & 0.04 \\
2 & 0.26 & 0.18 & 0.06 \\
\hline
\end{tabular}
\end{center}

(i) Show that $\operatorname { Cov } ( X , Y ) = 0$.\\
(ii) Find the conditional distribution of $X$ given that $Y = 2$.

\hfill \mbox{\textit{OCR S4 2007 Q3 [7]}}