\includegraphics{figure_4}
An engineering project is modelled by the activity network shown in Figure 4. The activities are represented by the arcs. The number in brackets on each arc gives the time, in days, to complete the activity. Each activity requires one worker. The project is to be completed in the shortest time.
- Calculate the early time and late time for each event. Write these in boxes in Diagram 1 in the answer book. [4]
- State the critical activities. [1]
- Find the total float on activities D and F. You must show your working. [3]
- On the grid in the answer book, draw a cascade (Gantt) chart for this project. [4]
The chief engineer visits the project on day 15 and day 25 to check the progress of the work. Given that the project is on schedule,
- which activities must be happening on each of these two days? [3]