5 The times, in months, taken by a builder to build two types of house, \(P\) and \(Q\), are represented by the independent variables \(T _ { 1 } \sim \mathrm {~N} \left( 2.2,0.4 ^ { 2 } \right)\) and \(T _ { 2 } \sim \mathrm {~N} \left( 2.8,0.5 ^ { 2 } \right)\) respectively.
- Find the probability that the total time taken to build one house of each type is less than 6 months.
- Find the probability that the time taken to build a type \(Q\) house is more than 1.2 times the time taken to build a type \(P\) house.